The Bulgarian Nuclear Power Plant (NPP) "Kozlodui" has registered yet another record in the production of electricity by reaching its nine-month production goal 41 days earlier.
The planned nine-month quantity of 10 257 123 MWh has been reached Wednesday. A total of 11 200 000 MWh are expected to be produced by the end of September
The good production results have been made possible due to the reduction of the time of the annual renovation of the NPP's fifth block.
Representatives of the NPP say further that Thursday, the fifth block has began to work with 100% of its capacity, while the sixth block was going be stopped for its planned annual renovation and would function with 82% of its capacity.