European Commission Grants Greece 1 Billion Euros for Renewable Energy Projects
With the aim to bolster renewable energy infrastructure, the European Commission has greenlit funding of 1 billion euros for two key projects in Greece
Bulgaria's Ministry of Economy has ordered the Electricity System Operator, ESO, to stop imposing restrictions on the production of energy by wind farms and photovoltaic plants on a regular basis.
Bulgaria's Ministry of Economy, Energy and Tourism (MIET) requires ESO to justify each restriction by publishing proof on its website, according to reports of Capital daily.
The regular capacity restrictions on renewable energy plants were explained with the imbalance between electricity production and consumption.
The restrictions concerned 40% of the grid-connected renewable capacity.
To defend the step, ESO noted that in Q1, 2013 Bulgaria's electricity exports had decreased by 22. 5 % on the year, while domestic consumption of electricity had fallen by 13.07%.
The restrictions caused the Bulgarian Photovoltaic Association (BPVA) to issue a number of letters of protest, claiming that the measures had been illegal.
"The spate of accusations against green energy seeks to justify the series of wrong political decisions which pushed Bulgaria's energy sector from deficit in January 2010, when electricity exports were stopped, to overproduction in March-April 2013" the BPVA argued.
Meanwhile, caretaker Energy Minister Asen Vasilev suggested that owners of renewable energy plants had declared that the capacities had functioned 32 hours a day but he refused to name concrete offenders.
Capital Daily argues that the restrictions were "nearly illegal" as Bulgaria is under an obligation to purchase green energy.
Stressing that the ESO never explained why the cap had been set at 40%, the newspaper suggests that the restrictions were imposed not to remedy imbalances but to reduce green energy costs at the expense of other power plants.
Capital Daily points out that a number of owners of renewable energy power plants are suing ESO because the 40% capacity restrictions imposed on a total of 20 days so far, together with the grid access fee, have driven them to bankruptcy.
Prime Minister Rosen Zhelyazkov has reaffirmed that the “Balkan Stream” pipeline remains a functional and commercially viable energy project
Sofia recently hosted the fifth edition of the Green Transition Forum 2025, a major regional event focused on sustainable development
Deputy Energy Minister Iva Petrova emphasized at Green Transition Forum 5.0 that Bulgaria’s energy strategy hinges on modernizing grid infrastructure and securing long-term supply agreements
From July 1, 2025, electricity and thermal energy prices in Bulgaria are set to increase
From July 1, 2025, Bulgarian households are expected to see an average increase of just under 5% in their electricit
Since its commercial launch at the end of 2022, the Greece–Bulgaria gas interconnector (IGB) has transported more than 34.5 million MWh of natural gas