Bulgaria's Kozloduy NPP Updates: Sixth Unit Under Maintenance, Eighth Unit Site Expected Approved by Next Autumn
The sixth unit of the Kozloduy Nuclear Power Plant (NPP) is currently undergoing its planned annual maintenance
Bulgaria's Kozloduy NPP, photo by BGNES
Westinghouse Electric Company has received a contract to perform a feasibility study on a potential seventh unit at Bulgaria’s Kozloduy Nuclear Power Plant.
The required study will encompass a review of two potential designs: a reactor of VVER design utilizing equipment already purchased by the customer together with Westinghouse instrumentation and control (I&C) systems, fuel and a Toshiba Corporation turbine generator, and the construction and operation of a pressurized water reactor (PWR) 1000-1200 MW design.
The scope of the feasibility study includes an evaluation of the site, radioactive waste and spent fuel management, reuse of existing infrastructures and facilities, licensing, local economic aspects, and the profitability of the two reactor designs.
The Kozloduy Nuclear Power Plant has an excellent operational and safety record, which provides a strong basis to host an additional reactor at the site, Westinghouse has pointed out in a press release.
“We look forward to assessing the potential to bring our advanced and proven I&C and fuel products for VVER reactor designs at the site,” Yves Brachet, Westinghouse president for, Europe, the Middle East and Africa, has commented.
5 companies had submitted documents to develop a project for the new Unit 7 of Bulgaria's Kozloduy NPP.
The companies were Westinghouse, French Areva, Areva in a consortium with Mistubishi, Bulgarian company Risk Engineering and Australian Worley Parsons.
The initial assesment must be ready some 7-9 months after concluding the contract; by the end of 2013 the company must choose the site for the new Unit 7.
The Bulgarian government decided to build a 7th unit at the Kozloduy NPP after in March 2012 it gave up on the construction of a second Bulgarian nuclear power plant in Belene.
Subsequently, the centrist-right GERB government decided to install the 1000 MW reactor already produced for Belene by Russian contractor Atomstroyexport, a subsidiary of Rosatom, at the existing plant in Kozloduy.
At present, only the 1000 MW units 5 and 6 are operational at the Kozloduy NPP, after Bulgaria agreed to shut down the 440 MW units 1-4 in 2002 and 2006 as part of its EU accession talks under pressure from Brussels.
Bulgaria’s Energy Minister Zhecho Stankov has confirmed that the United States has not imposed any additional conditions for the temporary exemption from sanctions targeting Lukoil
The United States has granted Bulgaria a significant exemption from its sanctions on Lukoil
Britain has introduced a temporary exemption that permits continued business with two Bulgarian subsidiaries of the sanctioned Russian oil group Lukoil
Lukoil has announced that all of its gas stations across Bulgaria are operating as usual and will continue to do so without interruption
Martin Vladimirov, director of the Geoeconomics Program at the Center for the Study of Democracy, said in an interview with the Bulgarian National Radio that the most beneficial outcome for Bulgaria would be for a strategic Western investor to acquire Luk
Energy Minister Zhecho Stankov has reassured Bulgarian citizens that the country’s fuel reserves are sufficient to cover domestic needs for several months