Technical Glitch Halts Unit 6 of Bulgaria's Kozloduy NPP

The 1 000-MW Unit 6 of Bulgaria's "Kozloduy" Nuclear Power Plant has been switched off from the electric network of the country at 4:19 am Saturday.
The switch-off happened after an automatic tripping of one of the defense mechanism of the turbine generator.
The switch of the turbine generator, part of the conventional, non-nuclear section of the unit, had not led to the activation of the emergency defense of the reactor, the NPPs press office informs.
The radiation level in the area remains unchanged. The Nuclear Regulation Agency has been notified.
Experts are working to eliminate the problem and Unit 6 is expected to be back in function and in the electric network later on Saturday.
The other 1 000-MW unit – Unit 5, is working at 100% capacity.
We need your support so Novinite.com can keep delivering news and information about Bulgaria! Thank you!
- » Bulgarian Power Industry Gears up for Green Technologies
- » IEA: Global CO2 Emissions Rise to Worrying Levels after Historic Decline in 2020
- » Clean Energy: Bulgaria between Two Difficult Choices
- » Bulgaria Ranks 8th in EU in Electricity Generated by NPP
- » ContourGlobal Maritsa East 3 TPP Provided Emergency Repair of the Oxygen Supply System at the Municipal Hospital in Galabovo
- » Bulgaria Mulls Building Small Nuclear Reactor