The Belene nuclear power plant has been de facto frozen since the fall of 2009 when the previously selected strategic investor, the German company RWE, pulled out. Photo by Sofia Photo Agency
Bulgaria's government expects Russia's state nuclear company to withdraw its EUR 58 M claim at an arbitration court over delayed payments for its work on two nuclear reactors, the energy minister has said.
"I think they [the Russians] realized that it makes no sense to fill the pockets of lawyers for getting legal services and that the best thing they can do for the project is to withdraw their claim," Economy and Energy Minister Traicho Traikov said in an interview for the Bulgarian National Radio on Sunday.
According to the minister the withdrawal is likely to become a fact in a few days.
Two weeks ago Russia's state nuclear company Atomstroyexport took Bulgaria's NEK to an arbitration court for EUR 58 M over delayed payments for its work on two nuclear reactors.
The next day the Bulgarian company said it is ready to strike back with a EUR 61 M counter claim against Atomstroyexport over delayed payments for purchases of old equipment for the plant, worth about EUR 300 M.
Minister Traikov explained on Sunday that the Bulgarian side has offered Moscow a few options on how to settle the scores without resorting to the arbitration court.
"One of the proposals they received suggests that instead of being involved in court battles, the two companies settle the claims by offsetting," said Traikov, but added that the Bulgarian company is ready to lodge a counter-claim should Russia perseveres.
Russia's response is expected at the beginning of the week.
In the middle of June Bulgaria said that Belene nuclear project will be frozen for another three months as of July to have time to catch up with the back office work and get more information about the cost of the project.
Bulgaria and Russia have been unable to agree on the major bone of contention - the price for the construction of the 2000-MW Belene NPP.
Russia says the project construction price should be EUR 6.3 B. The Borisov government wants to set the price at as little as EUR 5 B.
After it was first started in the 1980s, the construction of Bulgaria's second nuclear power plant at Belene on the Danube was stopped in the early 1990s over lack of money and environmental protests.
After selecting the Russian company Atomstroyexport, a subsidiary of Rosatom, to build a two 1000-MW reactors at Belene and signing a deal for the construction, allegedly for the price of EUR 3.997 B, with the Russians during Putin's visit to Sofia in January 2008, in September 2008, former Prime Minister Stanishev gave a formal restart of the building of Belene. At the end of 2008, German energy giant RWE was selected as a strategic foreign investor for the plant.
The Belene NPP has been de facto frozen since the fall of 2009 when the previously selected strategic investor, the German company RWE, which was supposed to provide EUR 2 B in exchange for a 49% stake, pulled out.