A file picture dated September, 2008, showing workers during the construction of the first 1 000 MW unit of the second nuclear plant of Belene, Bulgaria. Photo by EPA/BGNES
Bulgaria's state-run power grid operator NEK and Russia's state nuclear company Atomstroyexport have set up a financial working group on the Balkan country's planned Belene nuclear plant, it emerged on Friday.
The financial group has been set up under the provisions of Appendix 13 to the agreement for the construction of Belene nuclear power plant, signed by NEK and Atomstroyexport, which was contracted to build two 1,000 megawatt reactors at the Danube town.
Representatives of Atomstroyexport have agreed with the Bulgarian side and formally submitted to the Minister of Economy and Energy Traicho Traikov a roadmap, which maps out the most important steps to implement the project for the construction of Belene plant, Moscow announced.
No further details about the roadmap were immediately available.
The news comes days after Bulgaria's National Electricity Transmission Company NEK threatened to sue in Geneva Russia's state nuclear company Atomstroyexport over delayed payments on planned Belene nuclear plant.
The government in Sofia however was quick to point out that this is not a counter-claim to Moscow's lawsuit at an arbitration court in Paris, which is again on due payments on the nuclear project.
"The action was described as a "counter claim" just because the two sums in question are similar," a statement by the Economy and Energy Ministry said.
It was not immediately clear however why the Bulgarian authorities have picked the Swiss town for their lawsuit.
Meanwhile it emerged that Bulgaria and Russia will discuss possibilities for Russia's Atomstroyexport to withdraw its EUR 58 M claim at the negotiation table.
Bulgaria's National Electricity Transmission Company NEK has received a letter by Atomstroyexport to this effect on Tuesday. According to Minister Traikov negotiations will continue until August 12 at the latest.
Two weeks ago Russia's state nuclear company Atomstroyexport took Bulgaria's NEK to an arbitration court for EUR 58 M over delayed payments for its work on two nuclear reactors.
The next day the Bulgarian company said it is ready to strike back with a EUR 61 M counter claim against Atomstroyexport over delayed payments for purchases of old equipment for the plant, worth about EUR 300 M.
Minister Traikov explained on Sunday that the Bulgarian side has offered Moscow a few options on how to settle the scores without resorting to the arbitration court.
"One of the proposals they received suggests that instead of being involved in court battles, the two companies settle the claims by offsetting," said Traikov, but added that the Bulgarian company is ready to lodge a counter-claim should Russia perseveres.
In the middle of June Bulgaria said that Belene nuclear project will be frozen for another three months as of July to have time to catch up with the back office work and get more information about the cost of the project.
Bulgaria and Russia have been unable to agree on the major bone of contention - the price for the construction of the 2000-MW Belene NPP.
Russia says the project construction price should be EUR 6.3 B. The Borisov government wants to set the price at as little as EUR 5 B.
After it was first started in the 1980s, the construction of Bulgaria's second nuclear power plant at Belene on the Danube was stopped in the early 1990s over lack of money and environmental protests.
After selecting the Russian company Atomstroyexport, a subsidiary of Rosatom, to build a two 1000-MW reactors at Belene and signing a deal for the construction, allegedly for the price of EUR 3.997 B, with the Russians during Putin's visit to Sofia in January 2008, in September 2008, former Prime Minister Stanishev gave a formal restart of the building of Belene. At the end of 2008, German energy giant RWE was selected as a strategic foreign investor for the plant.
The Belene NPP has been de facto frozen since the fall of 2009 when the previously selected strategic investor, the German company RWE, which was supposed to provide EUR 2 B in exchange for a 49% stake, pulled out.
In Bulgaria, the overwhelming majority of complaints about high electricity bills are coming from households that rely on electricity for heating, particularly through air conditioners, the Energy and Water Regulatory Commission (EWRC) reported
Acting Energy Minister Traycho Traykov commented on Nova TV that the recent rise in fuel prices in Bulgaria is modest, with gasoline and diesel increasing by just three cents, reflecting crude oil quotations
Energy Minister Traycho Traykov briefed Prime Minister Andrey Gyurov that Bulgaria has received liquefied natural gas under contracts concluded before the recent escalation in the Middle East
The Consumer Protection Commission in Bulgaria has launched checks at fuel stations across the country to determine whether retail prices have risen and, if so, whether such increases are justified
The Energy and Water Regulatory Commission (EWRC) has set the price of natural gas for March 2026 at 32.60 euros per megawatt-hour, excluding access, transmission, excise, and VAT charges
By the end of 2026, Bulgaria will significantly increase its role as a regional energy hub, as the country’s gas transmission capacity from Greece is set to rise by 50%, while the interconnection with Romania will see its capacity doubled
Novinite 2025 in Review: A Year That Tested Bulgaria and the World
A Disgraceful Betrayal: Bulgaria's Shameful Entry into Trump's Board of Peace