Unit 6 of Bulgaria' Kozloduy NPP Shut Down Due To Drainage Pipe Issue

Business » ENERGY | October 28, 2013, Monday // 12:47
Bulgaria: Unit 6 of Bulgaria' Kozloduy NPP Shut Down Due To Drainage Pipe Issue Photo by bgonair.bg

Unit 6 of Bulgaria's Kozloduy nuclear power plant has been disconnected from the electricity grid on Monday, due to a drainage pipe issue.

The 1000-MW unit 6 of Bulgaria's Kozloduy nuclear power plant was disconnected from the country’s power grid at 07:30 am on Monday, October 28 due to a problem in the drainage system, a non-nuclear related issue, according to a media statement of Kozloduy NPP.

The Nuclear Regulatory Agency has been notified for the incident.

The drainage pipe problem was detected in the non-nuclear part of the Unit and there is no registered increase in radiation level at the plant.

Teams are working on to fix the drain pipe defect.

The other 1000-MW unit of the Kozloduy NPP, unit 5, works at 100% capacity.

The incident happens just two days after the completion of a scheduled 35 days annual overhaul of the unit that was put back online on Saturday.

We need your support so Novinite.com can keep delivering news and information about Bulgaria! Thank you!

Energy » Be a reporter: Write and send your article
Tags: Nuclear Regulatory Agency, Kozloduy, Nuclear Power Plant, NPP, annual overhaul, radiation level, non-nuclear, disconnect, drainage, Unit 6

Advertisement
Advertisement
Bulgaria news Novinite.com (Sofia News Agency - www.sofianewsagency.com) is unique with being a real time news provider in English that informs its readers about the latest Bulgarian news. The editorial staff also publishes a daily online newspaper "Sofia Morning News." Novinite.com (Sofia News Agency - www.sofianewsagency.com) and Sofia Morning News publish the latest economic, political and cultural news that take place in Bulgaria. Foreign media analysis on Bulgaria and World News in Brief are also part of the web site and the online newspaper. News Bulgaria